Leak test of the valves

The leak test of the valves determines the leak rates of the CE valves. The test enables faulty valves to be determined.

The test must be carried out at least every 100 days!

If the test is not carried out after 100 days, the hydrogen refuelling is blocked.

Test requirements

The following requirements must be met:

Test sequence

For the most part, the leak test is carried out automatically by the control module. The test duration is approx. 30 minutes.

Procedure

End of test

Counter ”Number of days since the last leak test”

The counter is reset to ”0 days when the leak test starts. The counter cannot be reset if the tank pressure at the start of the leak test is greater than 4.2 bar (absolute pressure).

Storage of the determined leak values in the CE module

The determined leak values are stored in the CE module when the CE module goes into the sleep mode (idle state). To prevent loss of data, the diagnosis command ”Power Down” is sent to the vehicle after the test has been run. This command places the control modules in the sleep mode.

The following points are important for the CE module to be placed in the sleep mode: